The deadlines, in one place
- 20 days
- from first furnishing to send a preliminary notice and protect the whole job
- 90 days
- after completion of the work of improvement to record a lien, if no notice of completion is recorded
- 60 days
- for the direct contractor after a notice of completion or cessation is recorded
- 30 days
- for subcontractors and suppliers after a notice of completion or cessation is recorded
- 90 days
- after recording the lien to file suit to enforce it, or the lien expires
The short answer
If you are a subcontractor or supplier in California, you generally have 90 days after the work of improvement is completed to record a mechanics lien.
But if the owner records a notice of completion or a notice of cessation, that window collapses to 30 days. A direct contractor gets 60 days from that same notice.
This is set out in California Civil Code sections 8412 and 8414.
Why the 30 day rule catches people out
Nobody tells you a notice of completion has been recorded. It is filed at the county recorder by the owner, and unless you are watching that county's index, the first you hear of it may be after your lien rights have already gone.
That is a sixty day swing on a deadline you cannot extend, triggered by a document you did not see.
What the lien itself has to say
Civil Code section 8416 requires the claim to name the person the claimant was employed by or furnished work to. That is why recorded liens are useful to more than just the parties: the document identifies who was running the job.
What we do about it
We index recorded mechanics liens, notices of completion and related documents from county recorders, so you can see what has been recorded against a contractor's jobs without watching the index yourself.
Coverage today is Orange, San Mateo, Stanislaus, Imperial and Modoc counties, with more being added. We would rather tell you that than let you assume statewide coverage we do not have.
Check the contractor before you rely on this.