The clock, step by step
The work is complete
Actual completion, or the owner occupies and uses the improvement after labor stops, or labor stops for 60 continuous days. Civil Code section 8180.
Owner may record a notice of completion
Recorded with the county recorder where the property sits. Optional for the owner, and most sophisticated owners do it because of what happens next.
Owner must notify claimants
The direct contractor, and everyone who gave a preliminary notice, must be sent a copy. If the owner skips this, the shortened deadline does not apply to the people who should have been told.
Lien windows close
Subcontractors and suppliers have 30 days from recording. The direct contractor has 60. Without a notice of completion, everyone would have had 90 days from completion.
Why it matters more than it looks
A notice of completion is a one-page document the owner records at the county. It does not say anyone was or was not paid. What it does is start a clock, and it starts a shorter one for the people furthest from the money.
A supplier who has not been paid on a job that finished in March normally has until June to record a lien. If the owner records a notice of completion on 1 April, that supplier has until 1 May, and the only way to know is to be watching the county's official records index or to have given a preliminary notice and received the owner's copy.
Most lost lien rights in California are not lost to a legal argument. They are lost to a deadline nobody saw move.
Lien deadlines with and without one
| Who is recording the lien | No notice of completion | Notice of completion recorded |
|---|---|---|
| Direct contractor | 90 days after completion | 60 days after recording |
| Subcontractor | 90 days after completion | 30 days after recording |
| Material supplier | 90 days after completion | 30 days after recording |
| Equipment lessor | 90 days after completion | 30 days after recording |
| Claimant the owner failed to notify | 90 days after completion | 90 days after completion, as if none were recorded |
The day you receive one
Count the days from recording, not receipt
The 30 days run from the date the county recorded the notice, which may be a week before the copy reached you. Pull the recording date from the document.
Check that it is valid
A notice of completion must be signed and verified by the owner, identify the property and the direct contractor, and be recorded within 15 days of actual completion. A defective one may not shorten anything, but do not bet the receivable on it.
Record the lien or get paid, inside the window
If the account is open, this is the moment to decide. A lien recorded on day 31 is a lien recorded too late.
Notice of cessation
The same rules apply to a notice of cessation, which an owner may record when labor has stopped for 30 continuous days on a job that is not complete. It is less common, it is used on stalled projects, and it shortens the lien window exactly the same way. If a job you supplied has gone quiet, assume one may be coming.
Questions people ask about notices of completion
This guide describes California law in general terms for people who have to act on it. It is not legal advice, and deadlines turn on facts specific to each project. When money is at stake, confirm the dates with construction counsel.
See notices of completion and liens by contractor
Search free, or run your whole vendor list in minutes.