The clock, step by step

Day 0

The work is complete

Actual completion, or the owner occupies and uses the improvement after labor stops, or labor stops for 60 continuous days. Civil Code section 8180.

Within 15 days

Owner may record a notice of completion

Recorded with the county recorder where the property sits. Optional for the owner, and most sophisticated owners do it because of what happens next.

Within 10 days of recording

Owner must notify claimants

The direct contractor, and everyone who gave a preliminary notice, must be sent a copy. If the owner skips this, the shortened deadline does not apply to the people who should have been told.

30 or 60 days after recording

Lien windows close

Subcontractors and suppliers have 30 days from recording. The direct contractor has 60. Without a notice of completion, everyone would have had 90 days from completion.

Why it matters more than it looks

A notice of completion is a one-page document the owner records at the county. It does not say anyone was or was not paid. What it does is start a clock, and it starts a shorter one for the people furthest from the money.

A supplier who has not been paid on a job that finished in March normally has until June to record a lien. If the owner records a notice of completion on 1 April, that supplier has until 1 May, and the only way to know is to be watching the county's official records index or to have given a preliminary notice and received the owner's copy.

Most lost lien rights in California are not lost to a legal argument. They are lost to a deadline nobody saw move.

Lien deadlines with and without one

Who is recording the lienNo notice of completionNotice of completion recorded
Direct contractor90 days after completion60 days after recording
Subcontractor90 days after completion30 days after recording
Material supplier90 days after completion30 days after recording
Equipment lessor90 days after completion30 days after recording
Claimant the owner failed to notify90 days after completion90 days after completion, as if none were recorded

The day you receive one

Count the days from recording, not receipt

The 30 days run from the date the county recorded the notice, which may be a week before the copy reached you. Pull the recording date from the document.

Check that it is valid

A notice of completion must be signed and verified by the owner, identify the property and the direct contractor, and be recorded within 15 days of actual completion. A defective one may not shorten anything, but do not bet the receivable on it.

Record the lien or get paid, inside the window

If the account is open, this is the moment to decide. A lien recorded on day 31 is a lien recorded too late.

Notice of cessation

The same rules apply to a notice of cessation, which an owner may record when labor has stopped for 30 continuous days on a job that is not complete. It is less common, it is used on stalled projects, and it shortens the lien window exactly the same way. If a job you supplied has gone quiet, assume one may be coming.

Questions people ask about notices of completion

Does a notice of completion mean the owner is disputing my bill?
No. It is a routine document many owners and lenders record on every project to close out lien exposure sooner. It is also the moment to make sure your bill is either paid or protected.
I never got a copy. Does the 30-day deadline still apply?
If you gave a preliminary notice and the owner failed to send you the notice of completion within 10 days of recording, the shortened deadline does not apply to you and you keep the 90 days from completion. If you never gave a preliminary notice, the owner had no duty to tell you and the 30 days run regardless.
Can I find out if one has been recorded on my job?
Yes, from the county recorder's official records index, by the property owner's name. Builder Records indexes notices of completion alongside mechanics liens in the counties we cover, so you can see them by contractor rather than by property.
What about public works?
Public projects use a notice of completion or acceptance recorded by the public entity, and the claim is a stop payment notice or a payment bond claim rather than a lien. The windows are different; this guide covers private works.

This guide describes California law in general terms for people who have to act on it. It is not legal advice, and deadlines turn on facts specific to each project. When money is at stake, confirm the dates with construction counsel.